2023 and 2024 Pavement Rehabilitation Project

2023 and 2024 Pavement Rehabilitation Project

The design street list for the 2023 and 2024 Pavement Rehabilitation projects is below.  The Design Treatments will include using a Stress Absorbing Membrane Interlayer (SAMI), overlays, and full-depth Reclamation (FDR). The streets listed in the table below are subject to change during design for many reasons, including underground conflicts, budgets, construction bid proposals, etc.  The final list will be made available when the Town Council awards the construction contract.  

Street
BeginningEndTreatmentTentative 2024 Schedule
Butterfield PlaceTharp DriveSouth End3" Mill and OverlayJuly to September
Constance PlaceCanyon RoadNorth End3" Mill and Overlay
July to September
Corliss DriveAshford PlaceMoraga Road4" Mill and Overlay
July to September
Corliss DriveWarfield DriveWakefield Drive3" Mill and Overlay
July to September
Corte FortunaCalle La MesaEast EndFull Depth ReclamationOctober to November
Donald DriveLaird DriveMoraga Road4" Mill and Overlay
June to August
Fairfield DriveMayfield PlaceSouth End3" Mill and Overlay
July to September
Lakefield RoadTharp DriveSouth End4" Mill and Overlay
July to September
Millfield PlaceDeerfield DriveEast End4" Mill and Overlay
July to September
Moraga RoadTBDTBDSpot RepairsJuly to September
Moraga RoadBuckingham DriveSky Hy DriveRubberized Cape SealJune to August
Paseo Del RioCampolindo DriveCalle La MesaFull Depth Reclamation
October to November
Redfield PlaceTharp DriveEast End3" Mill and Overlay
July to September
Springfield PlaceTharp DriveSouth End3" Mill and Overlay
July to September
St. Mary's RoadStafford RoadSt. Mary's PkwyCape SealJune to August
Via GranadaCalle La Mesa Moraga Road3" Mill and Overlay
July to September
Wimpole StreetWoodford DriveNorth End4" Mill and Overlay
July to September

NOTE: The street list is subject to change.

Project Team:

Project ManagerYao Miao, Town of Moraga, (925) 888-7028

Engineering Designer, Harris and Associates, Kourosh Iranpour, Project Manager (925) 969-8013

Resident Engineer Project Inspector, Substrate, Sunny Jhutti, PE, SE (415) 246-4920

Project Updates

To receive project updates, please sign up at Notify Me.