2020 Pavement Overlay Project

Special Announcement

November 18, 2020 – 2020 Pavement Overlay Project

The contractor started concrete repairs today to prepare for the grinding operation tomorrow on Calle La Montana and Calle La Mesa. Please observe the ‘No Parking’ signs. Note garbage pickup for tomorrow will not be affected.

November 12, 2020 – 2020 Pavement Overlay Project

The paving on Ascot Drive, Ascot Court, Ascot Place, Idlewood Court, and Cedarwood Drive has been completed.  The contractor will return for striping in the next few weeks, weather permitting. Thank you for the cooperation and patience during construction.

The contractor has returned to the Calle La Montana and Corte del Caballo to complete the storm drain improvements.  Due to the expected wet weather, the contractor may be working extended hours Monday through Friday, 7 AM to 5 PM and some Saturdays from 8 AM to 5 PM.  We apologize for any inconvenience and appreciate your patience during construction.  Please check the project webpage for information on schedule changes and project updates.


Project Team:

Project ManagerSharon Chan, Town of Moraga (925) 888-7028

Project Inspector, Arman Tajarrod, Harris & Associates (917) 868-8474

Contractor, Jeff Brandt, Bay Cities and Graving, Inc. (925) 532-6573

Project Background

An important Town Council Goal for 2020 was completion of the 2020 Pavement Overlay Project.  The Town use StreetSaver, a pavement management software, to select street candidates to be included in this year's project.  The 2020 Pavement Overlay Project will apply an overlay treatment to streets with "Poor" pavement conditions exhibiting major forms of distress.  

With the help of NCE, project's design consultant, the project documents were completed and advertised in April 8, 2020.  Public construction bid opening was held on May 5, 2020 and 6 bids were received.  The Town Council awarded a construction contract to the lowest responsible and responsive bidder, Bay Cities Paving and Grading, Inc., on June 24, 2020.  

The scope of work for this year's overlay project includes: removal and replacement of concrete curb, gutter and sidewalk; repair of storm drain pipes; construction of concrete curb ramps; asphalt base repairs; conform/wedge grind; asphalt overlay and removal and replacement of traffic striping.   The project is scheduled to begin the 1st week in September and completed in November 2020. Please expect contractors to be working Monday through Friday 7 AM to 6 PM.  A 3-week look ahead scheduled is available below. Please note schedules and work hours are tentative and subject to change. For more information on what to expect, please see the Pavement Management Program FAQ sheet below.

  1. October 28, 2020 - 2020 Pavement Overlay Project

    Paving operation is scheduled to take place Thursday, October 29,2020, on Ascot Drive, Ascot Court, and Ascot Place. Read on...
  2. October 20, 2020 - 2020 Pavement Overlay Project

    The 2020 Pavement Overlay Project is beginning the first of three phases of pavement overlay, grinding, and base failure repairs this week. Read on...
  3. August 26, 2020 Pavement Overlay Project

    The 2020 pavement overlay project will resurface 8 residential streets starting the week of August 31st. The contractor, Bay Cities Paving, will be lowering manholes and valve boxes and installing stormwater pollution prevention measures. Read on...
View All

Project Updates

To receive project updates, please sign up at Notify Me