Posted on: August 28, 2020

August 28, Canyon Road Bridge Update

IMG_9657 - modified

The bridge replacement project remains on schedule and budget.

The bridge replacement project remains on schedule and budget. The inbound lane of the bridge super structure is near completion. To support the new roadway, 240 feet of tall retaining walls are being constructed. The contractor is currently finishing the...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: July 3, 2020

July 3, Canyon Road Bridge Update

The Canyon Road Bridge Replacement Project is in its twelfth week of construction.

The July 3 early morning mass concrete pour of the stem, soffit, and abutments was a success. In the next two weeks, the contractor will form and pour the bridge deck. We appreciate everyone’s patience and cooperation. For more information, plea...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: June 25, 2020

June 25, Canyon Road Bridge Update

IMG_9657 - modified

The Canyon Road Bridge Replacement Project is in its tenth week of construction.

In the past two weeks, false work forming the bottom of the bridge has been completed, the stem and soffit are being formed, and rebar is being installed. The project is preparing for a critical early morning mass concrete pour on Friday, July 3, 2020, of...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: June 12, 2020

June 11, Canyon Road Bridge Project Update

The Canyon Road Bridge Replacement Project is in its eighth week of construction. Due to the project team's hard work and the cooperation of the community, the last day for the daily bridge closure will be June 18.

The Canyon Road Bridge Replacement Project is in its eighth week of construction.  In the past two weeks, abutment #1 footing and abutment #2 wall have been poured, and falsework installation has begun.  Due to the project team&rsquo...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: June 12, 2020

May 28, Canyon Road Bridge Project Update

The Canyon Road Bridge Replacement Project is in its sixth week of construction, and has reached a project milestone with the completion of the piles for the bridge abutments. Concrete pours for the abutment walls are scheduled to start on June 1.

The Canyon Road Bridge Replacement Project is in its sixth week of construction, and has reached a project milestone with the completion of the piles for the bridge abutments.  Creek diversion installation started last week, and the contractor is...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: April 30, 2020

April 30, Canyon Road Bridge Closure

Canyon Road Bridge construction has begun. The road will now be closed between Monday-Friday 9:00 am - 4:00 pm. Residents are urged to plan their travel accordingly. Emergency vehicles will still be allowed to access the road at all times.

The construction of the Canyon Road bridge has begun and requires the closing of the road Monday-Saturday from 9:00 am – 4:00 pm. These times were set up to allow early morning and late afternoon travel through the area to reduce the impact upon...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: April 25, 2020

April 25, Canyon Road Bridge Project Update

Beginning Monday, May 4, 2020, Canyon Road Bridge will be closed Monday through Friday and some Saturdays from 9:00 am to 4:00 pm to all traffic with the exception of emergency services.

Beginning Monday, May 4, 2020, Canyon Road Bridge will be closed Monday through Friday and some Saturdays from 9:00 am to 4:00 pm to all traffic with the exception of emergency services. We apologize for any inconvenience and appreciate your patience duri...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: April 13, 2020

April 13, Canyon Road Bridge Project Update

Construction will start on April 20th. Contractor has completed clearing and grubbing and the installation of Environmental Sensitive Area (ESA) Fence.

Construction will start on April 20th.  Contractor has completed clearing and grubbing and the installation of Environmental Sensitive Area (ESA) Fence.  The contractor will proceed with Phase 1 of the bridge construction which includes ...

Read on...

Town of Moraga, Canyon Road Bridge Project
Posted on: March 16, 2020

March 16, Canyon Road Bridge Project Update

The Town of Moraga has contracted with Bridgeway Civil Constructor, Inc to construct the Canyon Road bridge Replacement. Construction is scheduled to start April 20, 2020. The Contractor will be working Mon. - Fri. from 7 am- 6 pm and Sat. 8 am- 5 pm.

The Town of Moraga has contracted with Bridgeway Civil Constructor, Inc  to construct the Canyon Road bridge Replacement.  Construction is scheduled to start April 20, 2020.  The Contractor will be working Monday through Friday ...

Read on...

Town of Moraga, Canyon Road Bridge Project

News Flash

Posted on: September 16, 2020

FY 2020/21 Budget at a Glance

Fiscal Year 2020-21 Budget at a Glance Thumbnail

The Town’s Fiscal Year 2020/21 Budget at a Glance is available. This is the Town’s second annual budget brief document that summarizes the recently adopted FY 2020/21 Operating and Capital Improvement Program budgets. The Budget at a G...

Read on...

Town of Moraga, Home Page
Posted on: September 16, 2020

MCN Candidates' Night - Wednesday, September 30

This year’s Candidates’ Night will be held virtually via Zoom on Wednesday, September 30, from 7:00 to 8:30 pm. Meet the five Moraga Town Council candidates – Kendall Langan, Teresa Onoda, David Stromberg, Renata Sos and Ursu...

Read on...

Town of Moraga, Home Page
Posted on: September 16, 2020

Public Meeting Participation

Due to the Governor’s Executive Orders N-25-20 and N-29-20, which suspend certain requirements of the Brown Act, and pursuant to the orders by the Health Officer of the County of Contra Costa regarding COVID-19, the Town offices are closed to th...

Read on...

Town of Moraga, Home Page
Posted on: September 16, 2020

Emergency Preparedness

With the many wildfires burning throughout California, this is a good time to ensure you are prepared for an emergency. Have you taken these three important steps?

1 - Register for the Community Warning System (CWS) at CWS Alerts to receive evacuation and ...

Read on...

Town of Moraga, Home Page

News Flash

Posted on: July 21, 2020

We're Hiring!

School year position: Support and assist students with homework, long-distance learning plans, and provide supplemental enrichment activities and supervised outdoor opportunities. For more information and to apply visit CalOpps.

More info...

Additional Info... Town of Moraga, Parks & Recreation
Posted on: April 27, 2020

2020 Lamorinda Trails Challenge

Join with family and friends and get outside and enjoy the wonderful parks, trails, and open space in Lamorinda. Trail guide books can be downloaded online. Complete one of the two challenges to earn your Lamorinda Trails Challenge Pin!

Read on...

Town of Moraga, Parks & Recreation

News Flash

Posted on: August 26, 2020

August 26, 2020 Pavement Overlay Project

The 2020 pavement overlay project will resurface 8 residential streets starting the week of August 31st. The contractor, Bay Cities Paving, will be lowering manholes and valve boxes and installing stormwater pollution prevention measures. Please visit the...

Read on...

Town of Moraga, Pavement Management Projects
Posted on: August 26, 2020

July 8, 2020 Pavement Overlay Project

The final list of streets to receive an overlay treatment can be found below. Construction is expected to begin August 2020.

Town of Moraga, Pavement Management Projects

News Flash

Posted on: August 19, 2020

MCSP Community Meeting via Webinar - Wednesday, September 2, 6:00pm

A zoom webinar will be held to discuss the Moraga Center Specific Plan Implementation Project (MCSP-IP).  Town staff, including the Police Chief and Assistant Town Attorney, and the MOFD Fire Chief will be available to answer any questions you ma...
Read on...

Town of Moraga, Planning Department
Posted on: August 28, 2020

Small Business Relief Program

The Town has established a $30,000 Small Business Relief Program to support our local businesses with a portion of the Federal CARES Act funding the Town received. Please see the Small Business Relief Program page for more information.

Read on...

Town of Moraga, Planning Department