Town Of Moraga

Canyon Road Bridge Replacement Project

Newsflash:

Canyon Road Bridge is closed 9 AM - 4 PM, Monday through Friday.

Project Update:4-30-2020 - Canyon Road Bridge Closure

The construction of the Canyon Road bridge has begun and is moving into a new phase that will require the closing of the road Monday-Saturday from 9:00 am – 4:00 pm., beginning on Monday, May 4th. These times were set up to allow early morning and late afternoon travel through the area to reduce the impact upon residents. The Town is also taking advantage of the reduced traffic flows on Canyon Road due to the shelter-in-place requirements and school closures. The Town considered a number of traffic options during the construction period to ensure the safety of the construction workers, motorist safety, and the efficient construction of the project. Although the closure of Canyon Road, even for a portion of the day, was not the original plan, after Town staff examined the area with the contractor and observed the tight, compact area in which the construction is occurring, Town staff decided that the road closure option is the safest for both motorists and the construction workers and should allow the work to be done as quickly as possible, hopefully reducing the impact on residents. The Town will continuously monitor the road closure and the need for the road closure throughout the project, making adjustments or ending the closure when appropriate. The Town has also developed a system to expedite emergency vehicles through the area by notifying the construction crew if police, fire, or EMS units are responding to an emergency on the west side of the bridge. Once they are notified, the crew will open the roadway for emergency vehicles without delay. Moraga Police is coordinating this with the Moraga-Orinda Fire District, the Sheriff’s Office and other emergency services agencies in the area. 

Questions about the project should be directed to Sharon Chan, Assistant Engineer, at 925-888-7028. 

We apologize for any inconvenience and appreciate your patience.  

Project Update:4-25-2020

Beginning Monday, May 4, 2020, Canyon Road Bridge will be closed Monday through Friday and some Saturdays from 9:00 am to 4:00 pm to all traffic with the exception of emergency services. We apologize for any inconvenience and appreciate your patience during construction. 

Project Update:4-23-2020

Construction started on April 20th. Contractor has completed clearing and grubbing and the installation of Environmental Sensitive Area (ESA) Fence. The contractor will proceed with Phase 1 of the bridge construction which includes relocating the traffic signal located on the south side of the bridge. As a reminder when driving through the construction zone, please obey the speed limit and all traffic control. Traffic delays may occur for up to 15 minutes or longer. We apologize for any inconvenience and appreciate your patience during construction. 

Project Update:3-16-2020

The Town of Moraga has contracted with Bridgeway Civil Constructor, Inc to construct the Canyon Road bridge Replacement. Construction is scheduled to start April 20, 2020. The Contractor will be working Monday through Friday from 7 am to 6 pm and Saturday from 8 am to 5 pm. Please expect traffic delays up to 15 minutes or more. Town is working to minimize impact to the community. 

We are monitoring the COVID-19 situation which is evolving every day. Based on the latest definition of essential project in the latest Order of the Health Officer of Contra Costa County, Order No. HO-COVID-19-03 dated March 31, 2020, the Town has deemed this project as essential. Canyon Road is an evacuation route for the Town of Moraga. With this project, the Town will be reestablishing the excavation route to its full capacity.

We apologize for any inconvenience and appreciate your patience during construction. If you have any questions or concern, please contact the project team. 

Project Team

Resident Engineer

Inspector:  Harris and Associates

Brandon Hays

(760) 846-5842

Project Manager: Town of Moraga

Sharon Chan

(925) 888-7028

Contractor: Bridgeway Civil Constructors, Inc.

Joe Burgoon and Aaron Thorne 

Project Update Tree Removal:

The Canyon Road Bridge Replacement Project is scheduled to begin this spring. To clear the construction site right-of-way and make way for the new alignment, Julian Tree Care was contracted to perform tree removals along the eastern banks of the Moraga Creek. The work is scheduled to occur weekdays between 8:00 am and 5:00 pm, January 13 to 31, 2020. Due to limited operating space, traffic will be stopped for up to 15 minutes at a time to maneuver downed trees with a large crane into trucks. The Town apologizes for any inconvenience and appreciates your patience while this important work is completed. For questions please email Sharon Chan, Assistant Engineer, email schan@moraga.ca.us or call at 925-888-7028.  

Canyon Road Bridge Project Update Presentation:

The staff provided an update on October 10, 2018 to Town Council on the permanent bridge replacement project outlining the history of the project, bridge redesign due to impacts from the landslide, and the construction schedule. Tentatively, the bridge will be built in two phases, with the first half in 2019 and second half in 2020 to maintain traffic during construction. Click the link to view the presentation. Canyon Road Bridge Update Presentation.

Project Background:

The Canyon Road bridge over the West Branch of San Leandro Creek (also called Moraga Creek) is located within the Town of Moraga, just south of Constance Place and north of the Contra Costa County line. The bridge was originally constructed in 1936, is approximately 104 feet long, 24 feet wide and carries two lanes of traffic. The existing bridge is structurally deficient with a sufficiency rating of 48.8. A sufficiency rating of less than 50 qualifies a bridge for replacement according to the funding guidelines for the Federal Highway Bridge Program. The existing concrete deck is heavily abraded, rough, uneven throughout with spalling at the joints, and has pattern cracks throughout. Several of the wooden bridge railings and posts are broken and rotten. The existing bridge geometry is a safety issue for bicyclists and pedestrians who use the bridge to access a heavily used bike/pedestrian trail, the Lafayette-Moraga Regional Trail (maintained by East Bay Regional Park District), that serves recreational cyclists as well as nearby residents that walk to Joaquin Moraga Intermediate School adjacent to the northeast approach to the bridge.

Project Description:

The Town proposes to replace the existing bridge with a new clear-span bridge, approximately 120 feet long and 48 feet wide. The new bridge will accommodate two 12-foot travel lanes and two 8-foot wide shoulders on both sides, serving as bike lanes, and one 5-foot wide sidewalk to accommodate pedestrians on the west side of the bridge. 

As the bridge replacement will occur on the same alignment as the existing bridge, bridge construction will be staged in order to maintain public and emergency vehicle access across the creek. With staged construction, a portion of the existing bridge would be demolished while a portion of the new bridge would be constructed. Vehicles will be required to cross the bridge one-direction-at-a-time with temporary traffic signals at each end. With completion of the first stage of the new bridge, vehicles would be shifted to the new bridge, and then the remaining portions of the old, existing bridge would be demolished and the second half of the new bridge would be constructed. The alternative to staged construction would be to close the road, remove the bridge completely, and construct the new bridge all at once, with the advantage of construction being completed in a shorter timeframe. The alternative would cause an inconvenience to motorists and emergency responders as the shortest available detour route is over 13 miles long.

Project Status: 

In May 2014, the Town received the Authorization to Proceed with the Preliminary Engineering phase of the design and NV5 has been hard at work on the preliminary analysis, design and studies needed to identify project impacts to be assessed during the environmental process. The Town held an Agency Stakeholder Meeting on July 23. All affected agencies, departments, and utilities were invited to attend the meeting for a discussion with the Town’s Public Works staff and NV5 to learn about the project and its temporary and permanent impacts on the affected agency’s facilities and services.

The Town consulting engineer, NV5, incorporated the comments and requirements from all affected agencies into a preliminary plan that was presented at a Town Hall-style Community Meeting on October 15, 2014 at 6:00 p.m. 

A second Community Meeting will be held on January 20, 2015 at 6:00 p.m. to present a revised conceptual plan addressing the concerns received at the first meeting. Residents of Moraga and the unincorporated community of Canyon, along with commuters and trail users are invited to attend to learn about the project and what to expect during the construction.

A third and final community outreach meeting is anticipated prior to the start of construction to inform the community of the plan for construction staging and to introduce the construction management team, who will be on-site during construction and available for any questions throughout the duration of the project while in construction. Construction was originally scheduled for 2018; however, due to an adjacent landslide, the project requires plan modifications and is rescheduled to 2019. 

2017 Emergency Canyon Road Bridge Closure:

For more information on the Closure of the bridge click here