The Canyon Road Bridge Replacement Project is in its tenth week of construction.
In the past two weeks, false work forming the bottom of the bridge has been completed, the stem and soffit are being formed, and rebar is being installed. The project is preparing for a critical early morning mass concrete pour on Friday, July 3, 2020, of the stem, soffit, and abutment totaling 300 yards of concrete. To ensure the safety of the community and workers, the bridge will be closed beginning at 3:30 am and reopen no later than 3:00 pm. Click here for more information about the mass pour and bridge closure. Please visit the Project’s website for more information about the project. To sign up for project updates, please register at Notify Me.