Town Of Moraga

2014 Paving Repair Project - General Information

3 - Week Look Ahead Schedule (As of 8/26/14)

Streets
(for the limits for each street, please see the Street List)
August 25 - 29 September 1 - 5 September 8 - 12
25 26 27 28 29 1 2 3 4 5 8 9 10 11 12
M T W Th F M T W Th F M T W Th F
Rimer, Whitethorne, Oxford           H                  
Concrete Demo & Replacement3           O                  
Deerfield, Mayfield, Stonefield           L                  
Concrete Demo & Replacement3           I                  
Sanders, Larch           D                  
2" Grind4           A                  
Concrete Demo & Replacement3           Y                  
Danefield, Crossbrook                              
Base Repair1                              
Wedge Grind2                              
Concrete Demo & Replacement3                              
Alta Mesa, Camino Peral           H                  
Base Repair1           O                  
Wedge Grind2           L                  
1.5" Grind4           I                  
Concrete Demo & Replacement3           D                  
Country Club East/West           A                  
Wedge Grind2/2" Grind4           Y                  
Concrete Demo & Replacement3                              
Greenfield, York                              
Base Repair1                              
Wedge Grind2                              
Concrete Demo & Replacement3                              
Ashbrook, Warfield, Arroyo           H                  
Base Repair1           O                  
Wedge Grind2           L                  
1.5" Full Depth Grind5           I                  
Concrete Demo & Replacement3           D                  
Turk, Stafford           A                  
Base Repair1           Y                  
Wedge Grind2                              
Concrete Demo & Replacement3                              
Campolindo Streets, Woodford                              
Base Repair1                              
Wedge Grind2                              
Concrete Demo & Replacement3                              

1. Base Repair - Localized repairs of poor condition asphalt and will require temporary lane closures. Full road closures will NOT be expected during these repairs.

2. Wedge Grind - Surface layer of pavement will be removed by a milling machine before the street can be repaved with a new layer of asphalt. Partial road closures should be expected.

3. Concrete Demo & Replacement - Partial road closures should be expected during these repairs. Please pay attention to the barricades around wet concrete.

4. 1.5”/2” Grind – Contractor will use flaggers to keep traffic away from the milling machine and trucks catch the grindings. Partial road closures should be expected.

5. 1.5” Full Depth Grind – Contractor will use flaggers to keep traffic away from the milling machine and trucks catch the grindings. Partial road closures should be expected.