Rheem Boulevard Sinkhole Update

The winterization work on the 96 inch storm drain pipe under the sinkhole is performing well. Periodic inspections of the pipe are made when conditions allow. Surface work to protect the sinkhole is also performing well; the installed liner is protecting the walls of the sinkhole from rain and draining surface water into a temporary drain installed at the bottom of the sinkhole. Work continues to secure agreements with affected utilities required to submit a final package to Caltrans for approval, prior to obtaining contractor bids for permanent repairs. The work is expected to be completed by the end of this summer.