Commons Skatepark Parking Lot Update

This project has hit a milestone by completing the paving, after the successful lime treatment of soils and the placement of aggregate base. The next steps will be to grade and hydroseed the bioswale that parallels Moraga Road, install irrigation and landscaping, and stripe the parking stalls. The contractor projects the parking lot to be open to the public by the first week of March.