The utility relocation phase is complete and demolition of the bridge will begin on Monday, September 18, with work hours Monday through Friday from 7:00 am to 7:00 pm and on Saturday and Sunday from 7:00 am to 5:00 pm. After demolition, the next phase will include construction of approaches to the temporary bridge, reinforced abutments, and deep concrete pilings to protect the area from further landslide damage. Once that is completed, the installation of the temporary bridge and one-way signaling will be installed, with re-opening expected by the end of November. Please visit the project's homepage for more information.