2016 Pavement Design Service Contract

Town Council amended the Design Professional Services Agreement with Nichols Consulting Engineers to provide additional design services to complete the 2016 Pavement Reconstruction Project in an amount of $174,700. During project design, the outfall of a corrugated metal storm drain pipe that crosses Bollinger Canyon was found to be undermining the road and must be repaired and stabilized. The contract amendment includes potholing utility locations, geotechnical engineering, and environmental permitting and regulatory agency coordination.