The roadway reconstruction will consist of both recycling the existing roadway materials in place, a technology called Full Depth Reclamation (FDR), and placing a new layer of asphalt on top.  The pavement construction consists of four phases: 1) pulverize and mix pavement in-place; 2) remove of top few inches for grading; 3) re-mix material with cement; and 4) paving new asphalt.

Street Name Begin End Treatment
Bollinger Canyon Road St Mary's Road Joseph Drive Full Depth Reclamation
Corliss Drive Wakefield Drive Camino Ricardo Full Depth Reclamation
Larch Avenue #1160 Larch Avenue Camino Pablo Full Depth Reclamation