The Town’s Pavement Management Program had identified a list of potential street segment candidates categorized with Pavement Condition Index rated as “Very Poor/Failed” for the 2015 construction season that are appropriate for removing four (4) or five (5) inches of existing pavement and replacing with Hot Mix Asphalt (HMA) with or without Rubberized Hot Mix Asphalt (RHMA). HMA is a combination of aggregate bound together by asphalt cement, a product of crude oil while RHMA incorporates recycled rubber from tires.
Street Name Begin End Treatment
Alderbrook Place Fernwood Drive North End Surface Reconstruct:
Remove 4" AC/AB Replace with 4" HMA
Chalda Way 225ft N/O Williams Drive Rheem Boulevard Surface Reconstruct:
Remove 3" AC/AB Replace with 3" HMA
Country Club Drive Southard Court Sandringham South Surface Reconstruct:
Remove 4" AC/AB Replace with 2" HMA and 2" RHMA
Del Monte Court Carter Drive West End Surface Reconstruct:
Remove 4" AC/AB Replace with 2" HMA and 2" RHMA
Del Monte Way Carter Drive South End Surface Reconstruct:
Remove 5" AC/AB Replace with 3" HMA and 2" RHMA
Harold Drive Rheem Boulevard South End Surface Reconstruct:
Remove 4" AC/AB Replace with 2" HMA and 2" RHMA
Marie Place Larch Avenue West End Surface Reconstruct:
Remove 4" AC/AB Replace with 4" HMA
Natalie Drive Buckingham Drive Campolindo Drive Surface Reconstruct:
Remove 4" AC/AB Replace with 2" HMA and 2" RHMA
Scofield Drive Goodfellow Drive Rheem Boulevard Surface Reconstruct:
Remove 4" AC/AB Replace with 2" HMA and 2" RHMA
Winslow Place Corliss Drive North End Surface Reconstruct:
Remove 5" AC/AB Replace with 5" HMA